LN-Scheduler
Installation Instructions
LN-SCHEDL-0                                                                                      Code No. LIT-1201907
                                                                                                    Issued April 24, 2014
                                                                                                Supersedes June 12, 2012

Applications
                                                                                 FRONT VIEW
The LN-Scheduler features network-ready scheduling                                                                SIDE VIEW
                                                                                   4.5687 in.
and real-time clock functionality. The controller can                            (116.03 mm)
operate with LN Series controllers or other
multi-vendor open and interoperable LONWORKS®
controllers, and can display up to 250 network
variables.
The controller is based on the LONWORKS® technology         4.5685 in.
                                                          (116.03 mm)
for peer-to-peer communication between controllers.
North American Emissions Compliance
United States

 This equipment has been tested and found to                                     BOTTOM VIEW
 comply with the limits for a Class A digital device
                                                                                                            1.4754 in.
 pursuant to Part 15 of the FCC Rules. These limits                                                       (37.475 mm)
 are designed to provide reasonable protection
 against harmful interference when this equipment is                              BACK VIEW
 operated in a commercial environment. This                                        3.3959 in.
 equipment generates, uses, and can radiate radio                                (86.255 mm)

 frequency energy and, if not installed and used in
 accordance with the instruction manual, may cause
 harmful interference to radio communications.
 Operation of this equipment in a residential area is                                                      3.4100 in.
                                                                                                         (86.614 mm)
 likely to cause harmful interference, in which case       3.2500 in.
                                                          (82.55 mm)
 the user will be required to correct the interference
 at his/her own expense.

Canada

 This Class (A) digital apparatus meets all                                         2.3620 in.
                                                                                  (59.994 mm)
 requirements of the Canadian Interference-Causing
 Equipment Regulations.
                                                                  Figure 1: Casing Dimensions, in. (mm)
 Cet appareil numérique de la Classe (A) respecte
 toutes les exigences du Règlement sur le matériel
 brouilleur du Canada.
                                                         Mounting
Installation                                             Three mounting scenarios are available for the
Dimensions                                               Scheduler casing: North American Electrical Box,
Figure 1 shows the LN-Scheduler dimensions.              European Electrical Box, and DIN Rail.

                                                                         LN-Scheduler Installation Instructions               1
North American Electrical Box                                     7. Connect the power and network communication
To mount the North American Electrical Box:                          wires. See Power Wiring and Communications
                                                                     Wiring) for more information.
1. Remove the Scheduler panel from the device by
   gently pressing on the panel and pulling the front             8. Reattach the front panel to the base plate by
   panel outward (Figure 2).                                         pressing gently on the Scheduler until the panel
                                                                     clicks into place.
                                                                  European Electrical Box
                                                                  Follow the steps in the North American Electrical Box
                                                                  section.
                                                                  DIN Rail
                                                                  To mount on a DIN rail:
                                                                  1. Remove the Scheduler panel from the device by
                                                                     gently pressing on the panel and pulling the front
                                                                     panel outward (Figure 2).
                                                                  2. Break off the tabs to expose the DIN rail channels
                                                                     in the base plate (Figure 4).

                                                                                           Wire exit hole
                                                                                         break-off cover
            Figure 2: Removing the Panel

2. Select a mounting location.                                      Break-off tabs for
                                                                     Din Rail mounting
3. Pull the power and network communication wires
   until they extend 6 in. (152 mm) from the electrical
   box.
4. Pull the power and network communication wires
   through the wire exit hole (Figure 3).
                                        1
       3                  2                                   3

                                                                       Figure 4: DIN Rail Installation – Break Off

                                                                  3. Break off the cover from the exit hole (Figure 4)
                                                                  4. Pull the power and network communication wires
       4                                                  4
                                                                     through the wire exit hole.

       3                      2                       3

           1. Wire exit hole
           2. Mounting screw holes for 2x4 electrical boxes
           3. Mounting screw holes for 4x4 electrical boxes
           4. Mounting screw holes for 1/4 DIN electrical boxes

           Figure 3: Mounting Screw Holes

5. Position the base plate on the electrical box.
6. Mount the base plate using the screws provided
   with the electrical box.

2     LN-Scheduler Installation Instructions
5. Slide the back plate onto the DIN rail (Figure 5).     Wiring
                                                              IMPORTANT: Make all wiring connections in
                                                              accordance with local, national, and regional
                                                              regulations. Do not exceed the LN-Scheduler
                                                              Panel’s electrical rating.

                                                              IMPORTANT: Take reasonable precautions to
                                                              prevent static discharges when installing or
                                                              operating the device. Discharge accumulated static
                                                              electricity by touching a securely grounded object.

                                                          Power Wiring
                                                          Scheduler device power requirements: 24 VAC/VDC,
                                                          +15%, Class 2. Use transformers of 100 VA or less.
             Figure 5: DIN Rail Mounted
                                                          The minimum cable section for power wiring is of
                                                          18 AWG. We recommend using the heaviest gauge
6. Connect the power and network communication            wire based on a maximum of 14 AWG and a minimum
   wires. See Power Wiring and Communications             of 18 AWG.
   Wiring for more information.
                                                          If you are applying power to more than one device, use
7. Reattach the front panel to the base plate by          the following method to calculate power requirements
   pressing gently on the Scheduler until the panel       of the transformer:
   clicks into place.
                                                          •     Add the maximum power consumption of all
Location Considerations                                         devices together and multiply by 1.3.
For proper installation and subsequent operation of the
                                                          •     If the resulting number is higher than 100 VA, use
Scheduler controller, follow these recommendations:
                                                                multiple Class 2 transformers. Do not interconnect
•   Allow for proper clearance of device casing, wiring         the outputs of Class 2 transformers or power
    terminals, and service pin for easy access,                 sources unless listed for such connections.
    hardware configuration, and maintenance.
                                                          For multiple devices powered from the same
•   Record the Neuron® ID number located on the           transformer, maintain consistent polarity between all
    inside of the device casing for commissioning the     controllers. Connect the COM terminals from each
    device.                                               controller to the same terminal on the secondary side
                                                          of the transformer.
•   Install at the following environmental conditions:
    Ambient temperature: 32 to 158°F (0 to 70°C)                        CAUTION: Risk of Electric Shock.
    Relative humidity: 0 to 95%, noncondensing                          Disconnect the power supply before
•   Ensure proper ventilation of devices, and avoid              !      making electrical connections to avoid
    area where corroding, deteriorating, or explosive                   electric shock.
    vapors, fumes, or gasses may be present.                            MISE EN GARDE : Risque de décharge
                                                                        électrique.
                                                                        Débrancher l'alimentation avant de
                                                                        réaliser tout raccordement électrique afin
                                                                        d'éviter tout risque de décharge
                                                                        électrique.

LN-Scheduler Installation Instructions                                                                               3
We recommend using an external fuse on the 24 VAC             The LN-Scheduler controller also has a built-in network
secondary side of the transformers to protect all             jack (1/8 in. [3.5 mm] mono male audio jack) that can
devices against power line spikes (Figure 6).                 be used to connect to the LON network. This network
                                                              jack is located on the bottom of the device (Figure 8).

                                                                              Figure 8: Bottom View

                                                              Setup and Adjustments
                Figure 6: Power Wiring                        Commissioning
                                                              To commission a device and add it to a LONWORKS
Communications Wiring                                         network, you need to use the device plug-in as well as
The approved cable type for LON communications is             the .xif and .apb files. To obtain the necessary files:
Level IV 22 AWG (0.65 mm) UNSHIELDED. You can                 Note: The device commissioning instructions only
use both one-pair and two-pair wires. The LON                 apply when you are using a LONWORKS Network
communication wire is polarity insensitive and can be         Services (LNS®) network management tool, such as
laid out in either bus, star, loop, or free topology.         LN-Builder.
Connect both wires to the NET terminals of the                1. Run the installation setup to install the device
controller. If you are inserting multiple wires in the           plug-in and the latest version of the .xif and .apb
terminals, properly twist wires together prior to inserting      files into your computer. The .xif and .apb files
them in the terminal connectors (Figure 7).                      install in the C:\LonWorks\Import\JCI folder.
Note: Johnson Controls strongly recommends using              2. Register the plug-in into the network database. By
the bus topology network configuration for all LON               doing this, you create the device template that is
communication wiring, as it allows for easy                      used to commission the device.
troubleshooting.
                                                              3. Commission the device using the proper device
                      LN-Scheduler                               template and .apb file with your network
                NET B                   Network
                                                                 management tool.
                NET A
                                                              Note: If you download an improper .apb file into the
                                                              device, you may damage the Neuron chip in your
                     Controller 2                             controller. The controller may become unusable.
               NET                                            Neuron ID and Service Pin
                 GND                                          To commission a device and add it to a LONWORKS
                                                              network, you need the Neuron ID of the device. There
            Figure 7: Communications Wiring                   are two methods to obtain the Service pin number.
                                                              To locate the Neuron ID number, perform one of the
Note: For additional information about network                following procedures:
topology and wire-length restrictions, refer to the
Echelon® Junction Box and Wiring Guideline for                1. Manual entry: The Neuron ID address and bar
Twisted Pair LONWORKS Networks                                   code are located on either the top panel of the
(Part No. 005-0023-01).                                          device (surface and DIN rail models), or inside the
                                                                 casing of the device (flush mount models).
    IMPORTANT: Use proper terminations on the                 2. Service pin: Press the service pin on the device to
    network, according to the type of network topology           broadcast the Neuron ID on the LONWORKS
    you are using. Failure to do so might result in              network. The Service pin on the Scheduler is
    communication errors between controllers. Do not             located on the bottom right of the device (Figure 8).
    use multiple gauges of cable on the same
    communication bus, as this may also result in
    communication errors.

4        LN-Scheduler Installation Instructions
Repair Information                                           Troubleshooting
If the LN-Scheduler fails to operate within its              Table 1 describes possible troubleshooting problems
specifications, replace the unit. For a replacement,         and solutions.
contact the nearest Johnson Controls® representative.
Table 1: Troubleshooting
LN-Scheduler
 Problem                   Cause                    Solution
 Device is powered but     Fuse has blown           Disconnect the power. Wait a few seconds to allow the auto-reset
 does not turn on.         (Auto-reset fuse)        fuse to cool down. Check the power supply and the input/output
                                                    wiring. Reconnect the power.
                           Power supply polarity    Verify that consistent polarity is maintained between all controllers
                                                    and the transformer. Ensure the COM terminal of each controller is
                                                    connected to the same terminal on the secondary side of the
                                                    transformer (Figure 6).
 Device cannot             Absent or incorrect      Check power supply voltage between 24 VAC/DC and COM pins to
 communicate on the FTT    supply voltage           ensure that it is between acceptable limits. Check for tripped fuse or
 network.                                           circuit breaker.
                           Overloaded power         Verify the transformer used is powerful enough to supply all
                           transformer              controlled devices.
                           Network not wired        Verify the wire connections are correct.
                           properly
                           Absent or incorrect      Check the terminations.
                           network termination
 Device communicates       Network length           Check the total wire length to verify it does not exceed the
 well on short network                              specifications.
 but does not
                           Wire type                Check the wire type to verify it meets the specifications. Ensure you
 communicate on large
                                                    are using unshielded wire.
 network.
                           Network wiring problem   Verify the wire connections are correct.
                           Absent or incorrect      Check the terminations. Incorrect or broken terminations make the
                           network termination      communication integrity dependent upon a device’s position on the
                                                    network.
                           Extra capacitance        Verify that no extra capacitance is connected to the network other
                                                    than the standard FTT circuit and a maximum of a 10 ft (3 m) stub (in
                                                    bus topology).
                           Number of devices on     The number of devices on a channel should never exceed 64. Use a
                           network segment          router or a repeater in accordance to the specifications.
                           exceeded
                           Network traffic          Query node statistics to check errors. Use a LON protocol analyzer to
                                                    check network traffic.

LN-Scheduler Installation Instructions                                                                                       5
Technical Specifications
LN-Scheduler
 Power                   Voltage: 24 VAC/DC; +15%, 50/60 Hz, Class 2
                         Protection: 500 mA auto-reset fuse
                         Consumption: 8 VA
 Environmental           Operating Temperature: 50–122°F, (0–50°C)
                         Storage Temperature: -4–158°F, (-20–70°C)
                         Relative Humidity: 0–90% noncondensing
 General                 Processor: Neuron 3150™, 8 bits, 10 MHz
                         Memory: Nonvolatile Flash 64k (APB application,
                         Nonvolatile Flash 64k [storage])
                         Communication: LonTalk® protocol
                         Transceiver: TP/FT-10, 78 Kbps
                         Status Indicator: Green LEDs on outputs
                         Communication Jack Input: 1/8 in. (3.5 mm)
 Enclosure               Material: ABS Resin
                         Color: Off White
                         Dimension (FMT): 6 in. x 6 in. x 1.48 in. (151 x 151 x 38 mm)
                         Dimension (SMT): 4.57 in. x 4.57 in. x 1.48 in. (116 x 116 x 38 mm)
                         Shipping Weight (FMT): 0.88 lb (0.40 kg)
 Liquid Crystal          Type: Backlit
 Display (LCD)           Definition: 128 x 128 pixels
                         Display Area: 2.1 x 2.1 in. (53 x 53 mm)
                         Screen Saver: Customizable
 Electromagnetic         CE Emission: EN61000-6-3: 2007; Generic standards for residential, commercial, and light-industrial
 Compatibility                         environments.
                         CE Immunity: EN61000-6-1: 2007; Generic standards for residential, commercial, and light-industrial
                                       environments.
                         FCC: This device complies with FCC rules part 15, subpart B, class B
                         IC: This device complies with Class (A) digital apparatus requirements of the Canadian Interference-
                         Causing Equipment Regulations.
 Compliance              United States              UL Listed, File E107041, CCN PAZX, to UL 916, Energy Management
                                                    Equipment. FCC Compliant to CFR 47, Part 15, Subpart B, Class B.
                         Canada                     UL Listed, File E107041, CCN PAZX7, to CAN/CSA C22.2 No. 205, Signal
                                                    Equipment. Industry Canada, IECES-003.
The performance specifications are nominal and conform to acceptable industry standards. For application at conditions beyond these
specifications, contact the local Johnson Controls office. Johnson Controls, Inc. shall not be liable for damages resulting from misapplication or
misuse of its products.

                                                                                                                     Building Efficiency
                                                                                            507 E. Michigan Street, Milwaukee, WI 53202
                                             Metasys® and Johnson Controls® are registered trademarks of Johnson Controls, Inc.
                                    All other marks herein are the marks of their respective owners. © 2014 Johnson Controls, Inc.

6       LN-Scheduler Installation Instructions

Published in U.S.A.                                                                                                 www.johnsoncontrols.com

Позиції каталогу з цим документом

Документ виробника, опублікований як довідковий матеріал на обладнання, яке ми постачаємо. Правовласник може попросити прибрати його — приберемо.